Dec. 15, 2016 (Hagåtña) — Upcoming road projects will smooth out two well-traveled Dededo roads.
The Department of Public Works issued Notices of Intent to Award to the contractor for Macheche Avenue and Chalan Balako. The contracts are going through the approval process. Once the contract is signed by the Governor, the contractor will have to go through the permitting process. The contractor will then have 180 days to complete their projects.
ROAD: Macheche Avenue: Route 26, from Corenoso Street to Kalamasa Drive
CONTRACTOR: Hawaiian Rock Products
COST: $225,408
FUNDING: Local funds
PROJECT: Resurfacing project – reconditioning, milling and paving of existing asphalt concrete pavement
 
ROAD: Chalan Balako: Chalan Batangga to Y-Sengsong Road
CONTRACTOR: Hawaiian Rock Products
COST: $190,552.50
FUNDING: Local funds
PROJECT: Resurfacing project – reconditioning, milling and paving of existing asphalt concrete pavement